MPMLink Process Plan - Splitting QTYs during allocation

$
0
0

What is the best practice for being able to split quantities into different operations.  We are a bit confused here on how to proceed.

 

Assembly:  410-158444

Child parts:  401-158888 (QTY 4) needs to be split between 2 operations in the process plan.

 

Do we make a manufacturing view of this part, add another instance of 401-158888 with a qty of 2 and then from the occurrences tab reduce the number of the original 4 to 2?  Please provide any details you can (what UIs Explorers or browsers) to achieve this.

 

We have quite a few assemblies that the design view could be used in the process plan - except for the allocation of qty to operations.

 

Thanks,

Greg