Hi all,
We have a requirement of setting 2 different Date effectivities for the same Part Revision.
When we are using the Change Notice / Change Task approach of setting effectivity, there is a OOTB validation / Check that combines the 2 date effectivities and calculates the resultant effectivity.
Say for Eg,.
If CN1 / Change task 1 specifies effectivity as 31/3/2017 - Open ended
CN2 / Change Task 2 specifies effectivity as 10/5/2017 - Open ended
What we wanted is to set 2 different effectivities for that Part Revision namely
31/3/2017 - Open ended
10/5/2017 - Open ended
But system gives onl y1 effectivity , as the following effectivity ( seems it is merging and calculating)
31/3/2017
I can understand on why this is like this, because system determines that the Part Revision, as a Net result should be effective on the earliest date between 2 CNs.
My question is , how to bypass or over ride this check , so that we get 2 effectivities.
The reason for us wanting this is that we share the CN1/Change task 1 to Supplier 1 and CN2 / Change Task 2 to another Supplier 2 , via 2 different Projects (ProjectLink).
The behavior here is that system needs the "winning" CN (in this case CN1) to be shared to a supplier inorder to see the effectivity.
The effectivity 1 should not be visible to supplier 2, the effectivity 2 should not be visible to supplier 1.
We are in Windchill 11.0 M010.
Please give your valuable thoughts.
Thanks & Regards
Hari