Is there a way to choose for a file to advance the version of a document or CAD file when it is being checked in? It can be done after it has been checked in but that is AFTER a new iteration has already been made.
For example:
File.doc Version A.1 is checked out, revised and checked back in. This a new version and idealy I would like to be able to specify that so when I check it back in it becomes File.doc Version B.1. What happens now is it auto advances the iteration to A.2 then I have to manually "revise" it in windchill to be B.1. I can see this causing confusion in the future because the file history will say A.1-->A.2-->B.1 instead of A.1-->B.1.
Is there a setting or option I am missing that will allow me to do this? Has anyone run into this before? Thanks